How should a team track long-lead outage materials?

Link each critical material to the work it supports, an accountable owner and a verified status from procurement through staging.

What to consider

A purchase order alone does not establish readiness. Track supplier commitments, delivery dates, receipt, inspection where required, storage and reservation for the intended job. Escalate changes promptly, and have the appropriate technical authority review substitutions.

Practical steps

A practical example

A replacement rotor is linked to a critical outage job, but the purchase order alone does not prove it will be ready. The owner tracks the supplier's progress, shipping date, receipt, inspection and staging location. If delivery slips, the team identifies when a decision must be made and evaluates alternatives under site procedures. Status is reviewed against the job's actual need date, not only the outage start.

Explore the assessment

See how KANE approaches this work and what an engagement includes.

View the related assessment →

Related answer: Explore related guidance